Mauldin Butler Road Project Delay: Your Fall and Holiday Guide

October 22, 2026

The schedule on the official Building a Better Butler website still says construction begins in Fall 2026. Its FAQ page still gives an even older start date, early 2024, and a finish in late 2026. Neither date holds. On September 28, the City of Mauldin announced that SCDOT had delayed the project after the bids came in over budget, and that a new Request for Proposals will go out in 2027.

That moves the rebuild out of this fall and holiday season entirely. The orange cones you see near East Butler this fall belong to utility companies and the city's own paving program. Every event between now and the Christmas parade happens on East Butler as it is today.

The gap between the budget and the bids

SCDOT received only two bids. The lower one was $50.8 million, against a project budget of $34 million. That's a $16.8 million gap, roughly half again the budgeted amount. With only two bidders, SCDOT had little room to negotiate down to the budget.

The city says SCDOT expects to receive bids again in February, after reviewing contractor questions and putting together a more thorough bid package. The delay first came up publicly a week earlier. According to the Greenville Journal's council notes, City Administrator Seth Duncan told Mauldin City Council on September 21 that SCDOT had pushed the project back, that two bids had come in over budget, and that a revised RFP would follow in 2027.

The city's statement acknowledged how frustrating the news is for community members, "especially because this project has already been delayed several times," and noted that this delay is outside the city's control.

Here's how the timing works. The city's projects page estimates construction at 18 to 24 months once it starts. That clock can't start until a new bid package goes out, comes back, and is accepted. February is the next checkpoint. Even then, February only tells residents whether the bids fit the budget. It doesn't mean construction is starting.

What's actually happening on and around Butler this fall

Several separate efforts are scheduled or underway near the corridor this fall, and they're easy to mix up from the driver's seat.

Work Who Status per the city's fall 2026 updates
Utility relocations along the Butler corridor Duke Energy Wrapping up
Utility relocations along the Butler corridor Charter and AT&T Starting soon
City street paving City of Mauldin Scheduled to begin the week of Oct. 19, estimated three to four weeks
E. Butler Road bridge over I-385 SCDOT Rehabilitation completed this summer
Miller Road, Murray Drive to Corn Road SCDOT Recently repaved
Highway 276 through Mauldin SCDOT All lanes resurfaced in 2025
Ashmore Bridge Road SCDOT On the 2027 repaving list

The utility work is the first phase of Building a Better Butler. According to the city, SCDOT and Duke Energy had secured the needed rights-of-way by August 2025, and the relocations that began in November 2025 were expected to take about 24 months. So the crews you see near Butler this fall belong to the project, just not to the construction phase.

The city's paving program is separate from the Butler project. The city scheduled work to begin the week of October 19 on Brookbend Road, S Park Drive, Whatley Circle, Fargo Street, Holland Road and Moore Street. The city estimates three to four weeks, weather permitting. Brookbend is one of the five Butler intersections the rebuild plans to improve. Holland Road is also the Christmas parade route on December 5, covered below.

The road this season's events run on

Here's what's still waiting for the rebuild on the 1.7 miles from the Mauldin Senior Center entrance to US 276. The plans call for curb and gutter, a sidewalk on one side, a multiuse path on the other, medians, intersection upgrades at N. Main Street, Hyde Circle/Bon Air Street, Murray Drive/Fairfield Drive, Old Mill/Bethel Drive and Brookbend Road, and two new bridges over Gilder Creek in place of the existing culverts. The multiuse path is designed to connect to existing paths at the Mauldin Cultural Center and the Senior Center, and SCDOT expects the project to improve connections to City Center Village, BridgeWay Station and, eventually, the Swamp Rabbit Trail.

Those are the places on this season's calendar, and until the rebuild happens you'll get between them on today's road. Our summer guide to the East Butler axis mapped this stretch when the rebuild still looked closer. Here's how the fall and holiday calendar falls along it.

Mauldin Outdoor Amphitheater, 101 E. Butler Road

Friday Night Frights, Friday, Oct. 23. Free trick-or-treating runs from 5:30 to 7:30 p.m., followed by a screening of Monsters, Inc. at 7:30.

A Merry Mauldin Christmas, Thursday, Dec. 3, 5 to 8 p.m. The Mauldin Cultural Center lists the schedule:

  1. 5:00 p.m. The holiday market opens, along with pictures with Santa, train rides and food trucks
  2. 6:00 p.m. Live performances
  3. 7:00 p.m. Tree lighting ceremony
  4. 8:00 p.m. Event concludes

The evening also includes the Merry & Bright Holiday Light Trail and its photo stops. The holiday market and the tree lighting happen together, with local vendors on site from 5 to 8.

BridgeWay Station, at the other end of the corridor

On BridgeWay Station's calendar, the last week of October is mostly Halloween:

  • Family Flicks: Halloween Town, Wednesday, Oct. 28, at BridgeWay Station
  • Halloween at The Park, Friday, Oct. 30, at GE Vernova Park
  • Cars and Coffee, Saturday, Oct. 31, at BridgeWay Station

GE Vernova Park is the stadium where the Greenville Triumph played its first match on June 3, 2026, a 1–0 win over Forward Madison in front of a sold-out crowd. We wrote about the park's first season earlier this fall. Halloween at The Park brings a stadium night to the last week of October.

What's opening along the way

Development along the corridor is moving faster than the road project. The clearest example opens in early November.

Mountain High Outfitters has set its grand opening for 10 a.m. on Saturday, Nov. 7, according to the Greenville News. The Alabama-based outdoor retailer already has stores in Bluffton, Columbia and Myrtle Beach. The BridgeWay store will be its fourth in South Carolina and its 31st overall. The same report says the company carries more than 160 brands for camping, hiking and running, including Patagonia, Vuori, Hoka and YETI. Earlier Greenville News coverage placed the 6,197-square-foot shop at 1102 Via Corso Avenue.

Coupe's Corner is coming to East Butler Road itself. The Greenville News reported on September 25 that the downtown Greenville bar and lounge, known for its cocktails, food and entertainment, plans a second location on the corridor. The original is at 111 Augusta St. downtown and has built a loyal following over nearly three years. No opening date has been announced for the Mauldin location.

December 5 brings the season to Holland Road

The holiday season's biggest Saturday runs along the side streets. Breakfast with Santa, hosted by the Greater Mauldin Chamber of Commerce, runs from 9 to 11:30 a.m. at the Ray Hopkins Mauldin Senior Center, 203 Corn Road. Tickets are $7 for adults and $5 for children, sold at the Chamber office or by phone at 864.297.1323.

At 2 p.m., the Chamber's annual Christmas Parade starts at the Golden Strip Career Center, travels down Holland Road and ends at BridgeWay Station. That's the Holland Road on this fall's city paving list. The paving was estimated at three to four weeks from the week of October 19, which puts it well before December 5, weather permitting.

That Saturday covers both ends of the corridor. It starts with breakfast at the Senior Center on Corn Road, where the rebuild's 1.7 miles begin, and ends with the parade at BridgeWay Station, one of the places the rebuild is meant to connect. Between the two is the East Butler Road the rebuild hasn't touched yet, with Duke Energy's work wrapping up and Charter and AT&T's still to come. The next real update on when that changes is SCDOT's bid round in February, which the city has said it will report to residents as news comes in.

If the delay has you rethinking your plans, I'm glad to talk it through. Whether you're timing a sale, picturing life near BridgeWay Station or just want a local read on Mauldin, I follow these corridor projects closely for my clients. Reach out to Andreana Snyder to Schedule a Free Consultation, and we'll look at what the Butler Road timeline means for your street.

Work With Andreana

Building and maintaining relationships and achieving the goals of her clients are her top priorities. As an experienced agent with extensive market knowledge, She is committed to providing the very best service to her clients by being responsive, working diligently, and offering a stress-free approach to buying and selling. Work with Andreana today!